The same time we want to use milestones only with WBS-elements for basic POC
evaluation.
For instance for WBS we can attach several milestones with different POC,
like 10%, 50%, 80%.
What is the tool in the system to confirm that particular milestone is
reached? How can I change milestone status?
-----Reply Message-----
Subject: RE: Milestones
each milestone attached to a WBS element will have an actual date field open
for entery when u release the WBS element. this will determine if the milestone
has been achieved or not.
the %age entered in the milestone for POC will be considered in the progress
analysis.